Schedule for Design Development
Dates (12/1/99-2/2/01)
Tasks
12/1/99
Start
12/1-1/25/00
FPA Design Development
1/5-1/7
Issue Consultant Background
12/15/99-1/25/00
Consultant DD
1/26-2/8
Hanscomb Price DD set
2/9-2/29
Value Engineering and Revisions
4/13/00
Notice to proceed for CD from Zoo
4/18
Zoo signs contract
5/10
Receive soils report
4/19-5/9
Scope/budget/VE adjustments
4/19-6/13
FPA begin CD
5/23-6/12
FPA update for VE
6/13-7/5
FPA redesign floor plans
7/6-7/12
Review with Program Manager & Board
7/13-7/18
FPA finalize background drawings for consultants
7/19-9/12
Permit set CD (90% structural)
9/13-10/10
Complete CD
9/13-9/15
Arts Commission Phase II prep and review
9/18-10/27
Permit Processing
10/11-10/24
Zoo review CD for addenda
10/25-10/31
Zoo review addenda
10/30-11/15
Permit process addenda
10/11-12/5
Bid period
12/6-2/1/01 Award
2/2/01 Start Construction