Dates (12/1/99-2/2/01)
|
Tasks
|
|
12/1/99
|
Start
|
|
12/1-1/25/00
|
FPA Design Development
|
|
1/5-1/7
|
Issue Consultant Background
|
|
12/15/99-1/25/00
|
Consultant DD
|
|
1/26-2/8
|
Hanscomb Price DD set
|
|
2/9-2/29
|
Value Engineering and Revisions
|
|
4/13/00
|
Notice to proceed for CD from Zoo
|
|
4/18
|
Zoo signs contract
|
|
5/10
|
Receive soils report
|
|
4/19-5/9
|
Scope/budget/VE adjustments
|
|
4/19-6/13
|
FPA begin CD
|
|
5/23-6/12
|
FPA update for VE |
|
6/13-7/5
|
FPA redesign floor plans |
|
7/6-7/12
|
Review with Program Manager & Board |
|
7/13-7/18
|
FPA finalize background drawings for consultants |
|
7/19-9/12
|
Permit set CD (90% structural) |
|
9/13-10/10
|
Complete CD |
|
9/13-9/15
|
Arts Commission Phase II prep and review
|
|
9/18-10/27
|
Permit Processing |
|
10/11-10/24
|
Zoo review CD for addenda |
|
10/25-10/31
|
Zoo review addenda |
|
10/30-11/15
|
Permit process addenda
|
|
10/11-12/5
|
Bid period |
| 12/6-2/1/01 |
Award |
| 2/2/01 |
Start Construction |