Schedule for Pre Schematic Design
Dates (6/2/98-8/8/98)
Tasks
6/2/98
Start
6/2/98 - 6/15/98
Gather Site Background Data
6/2/98 - 6/22/98
Gather Master Plan Background Data
6/2/98 - 6/22/98
Gather Architectural Character Data
6/2/98 - 6/8/98
Review Master Plan for Retail / Food
6/2/98 - 7/31/98
Attend regular Meetings
6/16/98- 6/29/98
Tree Field Survey
6/23/98 - 6/29/98
Study Boundaries & Slope
6/23/98 - 7/8/98
Set Srchitectural Character Vocabulary
6/30/98 - 7/6/98
Review Master Plan & Early Project Docs
6/30/98-7/7/98
Meet w/ Maint, & Hort Staffs
6/30/98-7/1/98
Tree Evaluation
7/2/98-7/9/98
Retail Food & Service Report
7/10/98-7/13/98
Annotate Tree Survey & Date
7/14/98-7/27/98
Preliminary Circulation Elements & Site Review
7/27/98-7/29/98
Sketch Site Plan w/ Circulation
7/30/98-7/31/98
Review Education Bldg. / Arch. Character
7/30/98-8/3/98
Education Bldg. Site Plan
7/30/98 - 7/3/98
Zoo Director Review & Approve
8/3/98
Zoo Committee Review & Approve
8/4/98
Zoo Board Review & Approve
8/4/98-8/5/98
Finish Field Paoli Pre-Schematics
8/5/98 - 8/18/98
Begin Education Bldg, Design Development