Construction Administration: Master Project Schedule
| Date Scheduled |
Schematics |
Design
Development |
Construction
Documents |
Construction
Administration (CA) |
Project
closeout |
|
Aug 1, 1997 |
Sept 5, 1997 |
May 30, 1998 |
August 15, 1998 |
June 25, 1999 |
July 5, 1999 |
|
Mar 31, 1998 |
Oct 15, 1997 |
June 15, 1998 |
Sept 2, 1998 |
Nov 5, 1999 |
Jan 5, 2000 |
|
Jan 19, 1999 |
Oct 15, 1997 |
June 15, 1998 |
Jan 1, 1999 |
April 1, 2000 |
June 1, 2000 |
| 1997 | 1998 | 1999 | 2000 | ||||||||||||||||||||||||||||||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 1 | 2 | 3 | 4 | 5 | 6 |
| SK1 | DD1 | CD1 | CA1 | * | |||||||||||||||||||||||||||||||||||||
| SK2 | DD2 | CD2 | CA2 | * | |||||||||||||||||||||||||||||||||||||
| SK3 | DD3 | CD3 | CA3 | * | |||||||||||||||||||||||||||||||||||||
As you can see, the majority of the delays
occurred during the construction administration / construction phase. Because
UCSF was the general contractor and Pro West worked as construction managers for
UCSF, it took longer for information to travel because it had more people to move
through (both UCSF and Pro West). This is especially critical during
construction when even small delays in information can lead to long delays for
the trades at the site, and thus a late project.
<